Rawr Beauty, Kenilworth

A tired commercial unit turned into a brand new, stylish beauty salon. Three weeks, start to finish.

Sector
Commercial
Programme
3 weeks
Our scope
Full fit-out
Location
Kenilworth
After Before: a dated office unit with a grid ceiling and carpet tiles After: the finished Rawr Beauty salon with a plasterboard ceiling, lighting and new flooring
Before and after

From office unit to salon

Out went the old suspended ceiling and carpet. In went a new MF plasterboard ceiling, a treatment room, flooring, lighting and a full decoration.

The brief

We were contracted to convert a tired commercial unit into a brand new, stylish beauty salon, and we had three weeks to complete the job from start to finish.

Our own teams handled the ceiling, partitions and carpentry. Our network covered the electrics, flooring and decoration, and we finished by furnishing the salon ready to open.

Works schedule
  • W1Old suspended ceiling removed
  • W2New MF plasterboard ceiling installed
  • W3Partitioning to create a treatment room
  • W4New flooring
  • W5New spotlights and electrical work
  • W6Plastered and decorated throughout
  • W7Furnished, ready to open

Planning something similar? Tell us about it.

Call Email us
Email us

Tell us about your project.

What's it for? Pick any

Only used to reply to you. Privacy

Prefer your own email app? info@fgsheridanconstruction.com